One Timeline at a time
- A task can only be linked to one Timeline.
- If you try to import it into another Timeline, you’ll be prompted to confirm.
- Proceeding will unlink it from the original Timeline and re-link it to the new one.
Copied Timelines
- If you copy a Timeline that has linked tasks, the links stay with the original Timeline.
- In the copy, tasks will display with their dates but won’t be linked back to the Task list.
Key Takeaways
- Import project tasks into a Timeline to manage dates visually.
- Use chaining to set up sequential schedules automatically.
- Linked tasks keep Task lists and Timelines in sync.
- Tasks can only link to one Timeline at a time.
- Copied Timelines keep the dates, but not the task links.
Congratulations!
You have now completed this training module.
We hope this new knowledge helps you with getting the most out of Pronto.
Explore our other training modules to learn more about Pronto’s key features and how to use them based on your role.