How It Works

1. Import Tasks to Timeline

From the Gantt view, click the Ellipsis (⋯) menu and select Import Project Tasks.
This opens the Import Tasks to Timeline modal.

2. Select Import Project Tasks.

In the import modal you can:

  • Select one or multiple tasks to import.
  • Search for tasks by name.
  • Choose to display completed or deleted tasks if needed.

3. Set a start date for the imported tasks.

4. Choose whether to:

  • Chain tasks – each task will follow the previous one, using the default duration (3 days).
  • Unchained – all tasks start on the same date with the default duration.

5. Click Import. Tasks appear in the Timeline with their parent/child structure.

Editing and Managing Imported Tasks

  • Parents vs children
    • Parent tasks display as non-editable bars in the Timeline.
    • Child and grandchild tasks are editable. You can move or resize them directly on the Timeline.
  • Predecessor-successor relationships
    • Linked tasks will show dependencies. For example, if Task A finishes, Task B begins.
  • Linked tasks
    • The Link Task column shows which tasks are connected to the Timeline.
    • Linked tasks display a green date field in the Task list. Hovering shows the linked Timeline and project details.
    • You can unlink tasks by clicking the unlink button, this keeps the dates but removes the connection.