Use Constraints to control when a Timeline Item can start or finish.
- Double-click the Timeline Item
- Go to the Advanced tab
- Select a Constraint Type from the dropdown
- Choose the date the constraint should apply from
Available Constraint Types:
- Must start on
- Must finish on
- Start no earlier than
- Start no later than
- Finish no earlier than
- Finish no later than
Constraints help keep your Timeline aligned with fixed deadlines or scheduling rules.