Request Support

Lag

What is lag?

Lag allows you to add a delay between when a Predecessor finishes and a Successor starts.
The lag value is the number of days between the two linked Timeline Items.

How to Set Lag

Option 1: Via Right-Click Menu

  1. Right-click the Timeline Item
  2. Open the Predecessor or Successor tab in the pop-up
  3. Enter your desired Lag value (in days)

Option 2: Click and Drag

Click and drag the Successor Item forward or backward on the Timeline
— the system will automatically apply a Lag based on the gap you create