What is lag?
Lag allows you to add a delay between when a Predecessor finishes and a Successor starts.
The lag value is the number of days between the two linked Timeline Items.
How to Set Lag
Option 1: Via Right-Click Menu
- Right-click the Timeline Item
- Open the Predecessor or Successor tab in the pop-up
- Enter your desired Lag value (in days)
Option 2: Click and Drag
Click and drag the Successor Item forward or backward on the Timeline
— the system will automatically apply a Lag based on the gap you create